Progress Report
Floor Wise Update
Basement
• HVAC Hi & Low -side completed
• Wall & ceiling paint work s completed
• Fire hi & Low side work is completed
• POP Ceiling work is completed
• STP civil work in progress
• Electrical work with fixture fitting completed
L-Ground Floor
• Escalator, Travellator and Lift installation work completed
• AHU installation and ducting work completed
• Brand Floor tiling & ceiling paint work in progress
• Fire Line testing is completed
• POP ceiling work in progress
• Paint work in progress
• Lift lobby wall cladding completed
Ground Floor
• Lift and Escalator work completed
• Lift lobbies wall tile cladding completed
• Floor tile work is progress
• AHU hi & low side completed
• POP ceiling work in progress
• Board out work in progress
• Fire Line testing is completed
First Floor
• Escalator testing completed
• Floor tile laying work completed in common area
• Common Area services Hi & low side completed
• Lift area stone cladding is completed
• False ceiling work in progress
Second Floor
• Escalator testing completed
• Floor tile laying work completed in common area
• Fire staircase stone laying work is completed
• POP False Ceiling work in progress
• Services Hi & Low side work in progress
Third Floor
• Fire Line testing is completed
• Services Hi & Low side work in progress
• Capsule lift fabrication work in progress
• Lift lobby wall cladding work in completed
Fourth Floor - PVR
• Escalator testing completed
• AHU HI side & low work in progress
• Civil work in progress
• Fire low side work completed